Update (January 14, 2010) on the CSX RF&P Subdivision third-track installation project

 

CLICK PHOTOS TO ENLARGE THEM
This is a brief photo update (January 14) of the third-track project through Franconia Hill (signals now called "Fleet"). In the picture above, it's become plain that CSX intends to keep the old siding, which appears to be getting a switch into new Track 1. This siding is very short, suitable only for setoffs.

In the following photo, plans for the siding are evident as a rock train in the distance lays ballast for new Track 1:



This crane is fitted with a pile driver for whacking iron beams into the ground, which will support for a new wall to hold the cliff where it belongs:

What, pray, is that camera on the shanty for? Is the CSX timesheet department now online?
 
 
Here comes S415 grinding up Franconia Hill:
 

 

For previous reports on construction at this spot as well as end-of-new-track at the Franconia-Springfield Metro/VRE station, see below.

CSX RF&P Subdivision: Update on the bridge replacement project at Cameron Run (CFP102) as of January 29, 2010

Work continues apace at Cameron Run on the RF&P to replace the old two-track bridge with a new one having wider clearance between track centers. As of January 29, huge pilings had been driven into the ground--apparently about 45' deep apiece--and welders were preparing them for the framework that will go across their tops. When completed, the new bridge will be assembled on the framework, a crane will left out the old bridge, and the new bridge will be slid horizontally into place. Then, presumably, the pilings will be removed.
 
  
  
  
  
 
Fyi, my previous report on the Cameron Run bridge was dated December 2, and can be found below.